Project : compression station facility GR 03 HASSI R'MEL
Activity: change over upgreat the system ( change the wirring and equipment cards testing the all detections instruments.(Test DFI DGC & test fire alarm & test BDV-ESDV test hart DPIT-TIT...) With let compression station on ligne ( not shutdown)
Installation and maintenance of the control of the table's electric cables and instrumentation Change of control and power cards
Coordinate the subcontracting of electronic partners
Set up the test scenarios about the performance to be achieved
Assist and advise our clients about their issues
CTCO
Electrical Technician commissioning
01.2024 - Current
LTHE
Electrical Technician commissioning
01.2023 - 07.2023
IRMA G S
Electrical Engineer
03.2022 - 04.2022
Job overview
Integrated Shutdown at centrale electrical project Eldraouch Taref
From 07/05/2022 to 18 /05/2022 centrale electrical project tipaza Hadjret Ennous ( instrumentation )
Changeover upgreat system from MARK6 to MARK6 E ( change cable ; cart instrument ; testing ...) wit company Baker Hughes
GEBCO BENTINI
Electrical Technician commissioning
11.2020 - 10.2021
Job overview
Installation Of Fire & Gas Detection System (Detectors Manual Call Points& Devices, Audible And Visual Alarms And Panels)
Installation Of Instrument Control Panels/ Marshalling Cabinets, Local Panel & Junction Box